The proposed 2023 Downtown Capital Improvement Project (CIP) is one of the last projects to complete the downtown corridor improvements.

This project will replace water and sewer infrastructure and improve the alley surfacing and drainage in the alley between Main Street and 2nd Street in the downtown corridor from the south side of Callender Street to the north side of Geyser Street.

Shannon Holmes is the City’s public works director. Martha is the City’s project manager and will be the main contact for the project. Matt with TD&H Engineering is the contracted design engineer for the project.

 

Shannon Holmes: – [email protected]  (406) 222-5667

Martha O’Rourke: – [email protected] (406) 222-5667

Matt McGee: [email protected] (406) 586-0277

Current proposed project timeline:

  • End of January 2023: Complete the engineering designs of the project;
  • February 2023: Submit plans to DEQ and obtain approval for construction;
  • March 2023: Advertise the project plans for bid;
  • April 2023: Open bids and sign a contract with the winning contractor;
  • May - September 2023: Construction period;
  • No construction during the 4th of July festivities

Project Map

The City is committed to ensuring improvements are made efficiently to minimize inconvenience to residents and business owners.


Public meetings will be held weekly once construction begins.

Please follow the website and City Facebook page for updates on anticipated schedule and traffic control.